Pre-deployment Phase
         
 
May 23rd, 2007
May 23rd, 2007
 
 

This update covers the recent network outages.

During the last two weeks, 20/20 Communications all of a sudden began experiencing network outages. No two outages were caused by the same situation. Two outages not only took out Wireless Washtenaw customers but our entire ISP services we provide. This includes T1, Wireless Sylvan and Scio, DSL and Dial-up.

We also had failures that affected both Saline and Manchester Wireless Washtenaw. Then there were a separate sequential series of problems that kept Manchester down for two full days.

Of course this had to happen the very day I began calling Pilot Participants to ask them if they want to continue with a paid service now that the pilot was officially over.

Participants who signed up and were charged for a paid service as these outages occurred will be reimbursed for the days service was unavailable.

I’m not thrilled about writing this type of update. However, we at 20/20 Communications don’t want potential and current participants to think we believe this is acceptable service. We certainly do not.

 

 

 
 
Back To The WW Updates Page
 
Back To The Wireless Washtenaw Site
 
Sign-up Now
View All WW Updates
 
May 9th, 2007
May 2nd, 2007
April 25th, 2007
April 18th, 2007
April 11th, 2007
 
Media Relations
FAQ
Pricing and Availability
Contact Us
Washtenaw County WW Site
 
 
     
   
 
   
Search 20/20 Communications :
Copyright 2005 - 2007 20/20 Communications LLC.
All Rights Reserved